Towards the end of a large infrastructure project the tension rises, and conflicts between team members occur more frequently. This affects the productivity of the team, and takes the focus away from completing the scope. To restore order the project manager putts two people off the team and replaces them with others.What strategy does the project manager use?
A、Forcing
B、Avoiding
C、Compromising
D、Exchanging